Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

You can link this Workwear and Tools Issue with a project from the Projects list if the Project Costing functionality is turned on on the Administration > Settings > Project Costing form. If the items are being issued for multiple projects, the Project field can be moved from the Main tab as a column to the table on the Workwear and Tools tab. For this, use the Setting button on the toolbar.

If the Enable Project Tasks option is selected on the Administration > Settings > Project Costing form, you can link the entire document with a specific project task or different items of workwear and tools with different project tasks. By default, the Project Task column is available on the Workwear and Tools tabs. If needed, you can move it as a field to the Main tab. For this, use the Settings button on the toolbar.

Use the Project field to select the associated project. If the items were requested for multiple projects, the field can be used as a column on the Workwear and Tools tab –  for this, use the Settings button.

The Comment text box can be used to specify any additional information about this document.

The toolbar buttons

After filling out the tab, click the Save button to save your work. After filling out all the tabs, click Post to post the document without closing it or Post and close to post and close the document.

...