  • Project  - Identifies the project under which the subcontract is executed.

  • Subcontractor - Specifies the contractor responsible for executing the work.

  • Contract - The contract linked to the subcontractor agreement.

  • Subcontractor agreement - Refers to the formal document - agreement with the subcontractor.
  • Subcontractors WBS -Work Breakdown Structure assigned to the subcontractor.
  • Agreement
    1. Qty - Quantity of work or material defined in the agreement.
    2. Amount (Cur) - Gross contractual value before applying any deductions.
    3. Discount Amount (Cur) - Commercial discount, if any, agreed on the gross amount.

...

    1. Qty - Quantity invoiced by the subcontractor.
    2. Amount (Cur) - Amount invoiced excluding , excluding VAT.
    3. VAT (Current) - VAT on the invoiced amount.
    4. Retention (Cur) - Retention deducted from the invoice.
    5. Retention VAT (Cur) - VAT on the retention amount.
    6. Progress % - % of total contract value invoiced to date.

Filters and Parameters

Report date - Select on date of the report

...