Invoicing Method Change

Problem: How to change Invoicing Method of the Project from Milestone to Progressive?

Solution: Cancel posting of Project Milestones (CTR) and apply changes.


NOTE This action is possible for users with Administrator Access Rights
1. In order to change Invoicing Method of the Project, from Milestone to Progressive: Image Removed  

Go to Functions for Technicians and find Project Milestone (CTR) in Advance Tools:

Image Modified

Image Modified
2. As list of Project Milestones (CTR) is opened, Cancel posting of corresponding record for required Project:

Image Modified


3. Go back to Project, change Invoicing Type to Progressive and Save:

Image Modified