Problem: How to change Invoicing Method of the Project from Milestone to Progressive?

Solution: Cancel posting of Project Milestones (CTR) and apply changes.


NOTE This action is possible for users with Administrator Access Rights
1. In order to change Invoicing Method of the Project, from Milestone to Progressive

Go to Functions for Technicians and find Project Milestone (CTR) in Advance Tools:


2. As list of Project Milestones (CTR) is opened, Cancel posting of corresponding record for required Project:


3. Go back to Project, change Invoicing Type to Progressive and Save:


Thank you for being a FirstBIT customer!