Comment - Field for entering any additional notes, remarks, or internal instructions related to this certification.
Service Tab
Services
Displays the work items or services being certified for the current period.
...
Quantity – Quantity of work certified in this certificate
Amount (Excl. VAT) – Certified amount excluding VAT.
VAT % – Applicable VAT rate (e.g., 5%).
Retention Total (before retention) – Certified amount before applying retention.
Retention% – Retention percentage
Retention VAT – VAT portion attributable to the retained amount.
VAT Amount – VAT on the non-retained portion.
Total – Final amount payable, including VAT, after retention.
- Project Task – Specific task linked to the item.
Description – Detailed label or scope of work.
Project WBS – Work Breakdown Structure reference.
Requisition – Reference to the requisition document.
Comment – notes for clarification or remarks.
Summary Tab
The Summary Tab provides a consolidated view of key quantities and financial metrics throughout the subcontractor payment process, allowing quick comparison across different stages:
Agreement – Original contract quantity and value agreed with the subcontractor.
Payment Application – Quantity and value claimed by the subcontractor in submitted applications.
Payment Certificate – Quantity and value approved or certified by the main contractor.
Invoiced – Quantity and value formally invoiced for payment.
Each section displays:
Qty – units of work.
Amount – Monetary value in AED.
Deduction Tab
Used to record amounts deducted from the total payable value of a subcontractor’s payment certificate. Each line reflects a specific deduction applied according to contract terms, retention rules, or penalties.
Item – The deducted service, work item, or reason for deduction.
Qty & Price – Quantity and unit rate applicable for the deduction (if relevant).
VAT – Tax status for the deduction, indicating whether VAT applies or not.
Amount – Total deduction value before VAT.
GL Account – Ledger account where the deduction is posted.
Project WBS – Work Breakdown Structure reference for cost allocation.
Department – Department responsible for or related to the deduction.
Advance Offset
Shows recovery of advance payments already made to the subcontractor:
Advance Reference – Reference to the advance payment document.
Recovered Amount – Portion of advance deducted in this certificate.
Balance – Remaining unrecovered advance.
Additional Information
Includes optional and reference fields for internal notes or cross-references:
Remarks – Any remarks or justifications for certification.
Prepared By / Checked By / Approved By – Responsible personnel details.
Attachments – Supporting files or evidence linked to the certification.
Print Forms
Standard print layouts include:
Subcontractor Payment Certificate – Summarizes certified work, deductions, and payable amount.
Custom Forms – May include company logo, signature fields, and approval details.