Estimate Qty & Amount-The original planned quantity and value from the contract or BOQ, used as the baseline.
Progress Report Qty & %-The completed work so far, recorded through progress reports, shown as quantity or percentage.
Payment Application Qty & Amount-The portion of progress that the contractor is claiming in the current payment application. This may differ from the actual reported progress.
Payment Certificate Qty & Amount-The portion of the claim that has been approved by the consultant/client after review.
Invoiced Qty & Amount-The value already invoiced to the client, usually matching the certified amount, unless invoices are split or postponed.
If the "Show Summary for the Selected Row" option is enabled, the summary table is a subordinate table that filters and displays details related to the selected parent row.
Deduction tab
Used to list amounts deducted from the total payable value of a payment certificate or invoice.
...