- Issue Date- The date the issue was identified.
- Issue- A short title or summary of the problem.
- Content- Additional explanation or context (optional).
- Responsible- The person assigned to resolve or follow up on the issue.
- For Print Form- A Checkbox to indicate whether this issue should appear in the printed version of the progress report.
Print form
This Project Progress Report print form provides a structured summary of the project's physical progress for a specific period. It highlights-includes:
Project, contractor, and contractor/ client details.
Breakdown of work items by according to the project structure (WBS).
Units, estimated quantities, and quantities reported in the current period.
Percentage of work completed in this period and cumulative to date.
Total cumulative progress is displayed at the bottom
...
.
Issues table - populated from the Issues tab in the system and shown separately.
Remarks - populated from the Comments section in the Main tab.
Site Photos - displayed when picture attachments are added to the document.