create to do item in scheduling.
my to do list.
ToDo task progress update.
fill and update project progress report "By ToDo items" mode.
The Progress by To-Do Items mode helps track and update project progress based on individual tasks (To-Do Items) created in the Project Schedule. This helps:
...
The feature is included within the Project Scheduling and Project Progress modules.
ed to describe how to turn on, and how to use functionality.
create to do item in scheduling.
my to do list.
ToDo task progress update.
fill and update project progress report "By ToDo items" mode.To use the functionality,
Project Schedule → right-click BOQ line → Create To-Do Item.
Or create directly from the My To-Do List screen of Project scheduling.
In the To-Do List, fill in the following fields:
Duty: Defines the task name.
...
Author and Timestamps: Logs who created the task and when.