Scope

This article applies to FirstBIT ERP Contracting configurations starting from release 2.1.1.35.

Overview

The location where the Invoicing Method is specified has changed starting from release 2.1.1.35.

FirstBIT ERP Contracting releaseWhere the Invoicing Method is specified
Releases earlier than 2.1.1.35In the Project, on the Main Parameters tab
Release 2.1.1.35 and laterIn the Contract associated with the Project

The available Invoicing Methods include Regular, Progressive, and Milestone.

Releases Earlier than 2.1.1.35

In earlier releases, the Invoicing Method was specified directly in the Project on the Main Parameters tab.

Release 2.1.1.35 and Later

Starting from release 2.1.1.35, the Invoicing Method is specified at the Contract level.

To set or change the Invoicing Method:

  1. Open the relevant Project.
  2. On the Main Parameters tab, select the Customer and the Contract associated with the Project.
  3. Open the selected Contract.
  4. Specify the required Invoicing Method in the Contract:

The Invoicing Method configured in the Contract is used for the Project associated with that Contract.

Changing the Invoicing Method for an Active Project

For an active Project, the Invoicing Method can be changed in the associated Contract, provided that the Contract allows the field to be edited.

Therefore, if you need to change the Invoicing Method for an active Project in release 2.1.1.35 or later, open the Contract selected in the Project and check the Invoicing Method there.


Important

If you are using release 2.1.1.35 or later and cannot find the Invoicing Method in the Project's Main Parameters tab, check the Contract selected for the Project. The setting is maintained at the Contract level in these releases.




Thank you for being FirstBIT customer!