The Payment Application Received document is used to record a subcontractor’s claimed amount for work performed under a Subcontractor Agreement (SA). It provides the basis for certifying the value of work completed and, when configured, for recognizing related expenses in the financial accounts.

How to Create

The Payment Application Received document is generated from the Subcontractor Agreement.

Main Tab

Captures the general details and linkages of the document

If the Subcontractor Agreement Basis is set to Recognize Expenses by Payment Application, expense recognition and financial postings occur when the document is approved/posted

GL Transactions:

Dr Expense (based on the linked cost item and analytics)

Cr Unbilled Purchase (liability representing the subcontractor’s claim)

When the subcontractor’s invoice is later received, this liability is cleared to Payables

Services Tab

service tab description need to do properly. need to group as columns descriptions. as it is in the software. Agreement (Qty/amount), Payment application (Previous qty/ Previous amount/ Precious %, Current %, Cumulative %) and after that quantity, amount ant etc.
- we do not have retention VAT rate column. but you described this.
- did not described retention vat.

The Service tab provides a detailed breakdown of all work items or services being claimed by the subcontractor in a payment application.

    1. Quantity - The total number of units of work agreed in the SA for this item.
    2. Amount - Total value based on the linked Subcontractor Agreement.
  1. Previous Quantity
  2. Previous Amount 
  3. Previous %
  4. Current %
  5. Cumulative %

Summary Tab

Shows consolidated totals for the selected service line and the entire document.

If "Show Summary for the Selected Row" is enabled, the summary displays only the totals related to the specific subcontract service line currently selected. When disabled, the summary shows totals for the entire subcontract payment application document.

Deduction Tab

This tab is used to record deductions applied to the subcontractor’s claim, such as penalties, material supply recoveries, advance recoveries, or other contractual adjustments. Each deduction reduces the total payable amount to the subcontractor.

Advance Offset

Only the advance payment is recorded as an offset balance and entered into the prepayment field, regardless of the payment method (bank transfer, cheque, etc.). This advance is linked to the current document so that any subsequent linked document automatically carries forward the prepayment. The final accounting offset occurs in the Invoice Received document.

Additional Information Tab

This tab is for adding extra details related to the project