Structure for document description as you did before for Invoice.

Purpose of use. Need to explain , that doc is the part of company project BOQ, what agreed to assign to subcontractor.

This document will be used in future subcontractor tracking documents as a reference for qty, prices and Scope.

How to creare

From Purchasing section
From project management in project costing.
Based on Requisition 
As result of Suppliers tendering.

Main tab

Settings in the contract need to describe. Inportant to mark contract as subcontractor. also settings for VAT and  retention will be taken for SA from contract. 
Settings to recognize expenses at the time of payment application. Optionally it will be as GRN with stock GL, but for Expenses. Gl transaction will be done for dr Expense - cr Unbilled Purchase, later in invoice Unbilled purchase will be closed to the current payables. If not required, then expanses will be recognized by Invoice received as default,
Type (Initial, Revision, Variation). 

Inventory and services tab

Subcontractor WBS. if required work tracking by subcontractor provided Work Code. But it is linked with our project structure by linking WBSs.
Pick by project budget, Purchasing Prices buttons.

Cost Control tab

linked with SA document line , to see and analyze budget usage.
it displays amounts on current doc date. by project , project wbs, and expense item. Represent costs already recognized or initiated processing. need to describe columns.

Revision 

it works similar to Revision for estimation. Can be recorded before any doc processed for SA.

Variation

it works similar to Variation for estimation. but for Subcontractor agreement doc. can be registered only based on the latest version of agreement.

Additional information page

Print form



The Subcontractor Agreement represents the formal internal document used to record and manage the portion of the project BOQ that is assigned to a subcontractor for execution.
It defines the scope of work, quantities, unit rates, and total value agreed upon with the subcontractor.
This document serves as a base reference for all future subcontractor-related processes, such as Payment Applications, Payment Certificates, and Variation Orders, to ensure consistent tracking of quantities, rates, and scope against the project budget.

How to Create

The Subcontractor Agreement can be created through several paths, depending on the business flow:

  • From Purchasing → Subcontractor Management → Subcontractor Agreement

  • From Project Costing→ Subcontractors Management→Management Agreement

  • Based on a Requisition, converting internal material or service requirements into a subcontracting scope.

  • As a result of Supplier Tendering, a selected supplier from the tender comparison is finalized as a subcontractor.

Main Tab

  • Company – Entity responsible for the subcontract.

  • Contract – Main project or contract to which the subcontractor work relates.

  • Entity – The executing company (used in multi-entity environments).

  • Type – Defines document purpose:

    • Initial – Original agreement.

    • Revision – Updated version of agreement before execution.

    • Variation – Additional scope or changes to approved agreement.

  • Project – Links subcontracted work to a specific project.

  • Apply Retention – Activates retention logic as per contractual terms.

  • Calculation VAT at Retention Invoice – Ensures VAT is applied at the time of retention release.

  • Recognize expenses in Payment Application received – If enabled, expenses are recorded when the subcontractor submits a payment claim rather than at invoice stage.


Other Options

  • Delivery / Planned Start / Finish Dates – Define execution timeline.

  • Basis – Reference for scope or cost basis.

  • Comments – Internal remarks or notes.

Inventory and Services Tab

This tab defines detailed work items agreed with the subcontractor.

  • Subcontractor WBS – Optional code to identify work as defined by subcontractor.

  • Item – Description of BOQ or service item.

  • Content – Detailed description of work.

  • Quantity / UOM / Price – Defines the scope and rate of work.

  • Discount / VAT / Total – Price and tax calculation.

  • Project Task / Project WBS – Links subcontracted work with internal project structure for cost and progress tracking.

Functions

  • Add / Pick / Pick by Project Budget – Import items directly from project BOQ.

  • Purchasing Prices – Pulls prices from historical purchase data for reference.

Cost Control Tab

The Cost Control section provides a real-time link between the Subcontractor Agreement and project cost tracking.

  • Update Cost Control Table – Refreshes the table to display current budget and order amounts.

  • Displays values as of document date by:

    • Project / Project WBS / Expense Item

    • Budget Amount – Approved amount in project budget.

    • Orders and Agreements (Current / Other Remaining) – Committed amounts including current SA and previous documents.

    • Materials Delivered – Value of work delivered or goods received.

    • Actual Expense – Recognized or posted cost.

Revision

Revisions are used to modify the Subcontractor Agreement before any related documents (e.g., Payment Applications) are processed.
It works similarly to Estimation Revision, allowing updates in quantities, rates, or descriptions while maintaining version history.

Variation

Variations are used to record additional or modified work under the subcontract after the initial agreement is in use.
It functions like Variation in Estimation, but specific to Subcontractor Agreement.
A variation can be created only based on the latest version of the active agreement.

Additional Information Tab

Contains supplementary details for internal or reporting purposes such as:

  • Internal reference numbers

  • Subcontractor contact details

  • Custom attributes for reporting or classification

Print Form

A dedicated Subcontractor Agreement Print Form is available to formalize the contract.
The print form includes:

  • Agreement header information (Company, Subcontractor, Project, Dates)

  • Detailed list of agreed work items, quantities, unit rates, and totals

  • Retention and VAT terms

  • Signature and approval section