The Revision Functionality allows users to make changes to an existing project estimate without modifying the original version. A revision .

Revisions are typically used for:

  • Adjusting quantities due to scope changes

  • Updating the markup after negotiation

  • Incorporating approved variation orders

  • Aligning with client-approved BOQs

 It can be created by clicking “Create Revision” under the Estimates tab. This opens a new editable version of the estimate.

Image Removed

This option is available when the status of the Estimate document is New.

In a revision, users can modify:

  • Quantity

  • Markup percentage and amount

  • Total cost

  • Amount excluding VAT

  • VAT percentage

  • Item content or description

Unit cost (rate)/ Cost is locked and cannot be changed. This restriction ensures that pricing approved earlier remains consistent and auditable. If the unit rate must change, a new estimate line or variation order should be created instead.

Revisions are typically used for:

  • Adjusting quantities due to scope changes

  • Updating the markup after negotiation

  • Incorporating approved variation orders

  • Aligning with client-approved BOQs

Image Added

Image Added

In the new Project estimate document, the estimate type is automatically changed to "Revision", and a unique number is assigned to the Revision# field. This helps track and differentiate each revision version.

Image Added

Once changes are made, the revision can be posted and submitted for approval if required. The system keeps the original version for traceability.This function supports cost control, version tracking, and proper documentation of project changes without compromising pricing integrity.