1. Purpose of the Document

The Project Scheduling document is used to define the planned start and finish dates of project tasks. It helps structure the timeline and is essential for:-

  • Tracking the sequence and duration of tasks.

  • Providing visibility into the planned timeline of the entire project.

  • Supporting communication between the project estimation and execution phases.

 This document links with the latest estimation and provides the basis for generating progress reports and Gantt charts.

Note: Note- This option becomes available only when "Use Advanced Project Planning" is enabled in both the Contracting Settings and the Project’s Main Parameters page.

Image Modified

Image Modified

...

1. How to Create the Project Schedule

This document can be from two areas:created in two ways-

  • From the Project screen directly.

  • From the Costing Module:-
    Go to Project Costing → Project Management Documents → Project Scheduling

3. Main Tab Attributes

  • Project: Select from available projects.

  • Planned Start Date and Planned Finish Date: Indicates project duration.

  • Duration: Auto-calculated from the dates.

  • Estimation Version: Linked to the latest approved estimation document.

  • Status Flags: The system will highlight if the estimation has changed and scheduling needs to be updated.

Image Removed

Image Removed

4. Link to Estimation Document & Update Requirement

The schedule is linked to the latest Estimation Document. If changes occur in the estimation (e.g., variation orders, task deletions), the system flags the schedule as outdated.

What happens:

  • System shows a notification: “Project structure is outdated.”

  • You are prompted to regenerate or update the scheduling document.

  • This ensures alignment between project planning and budgeting.

5. Table Section: How to Fill & Columns Explained

The tabular part displays the Work Breakdown Structure from the Estimation. You can:

  • Add or adjust rows for tasks and subtasks.

  • Enter or edit:

    • Task Name

    • Assigned Person

    • Start Date

    • Finish Date

    • Predecessors (optional)

    • Status (e.g., Cancelled if removed via variation)

Note: Tasks marked as “Cancelled” reflect changes made in estimation or variation orders.

6. Gantt Chart View (Separate Topic)

...

2. Scheduling Document

When creating a new Project Scheduling document, the system automatically pulls the structure from the previously created Estimation. The user can then modify and adjust the schedule as needed.

Main tab

The Main tab is used to define general and essential details-

  • Project- The name of the project for which scheduling is done.
  • Project Schedule- The name of the schedule version.
  • Responsible- The person in charge of this schedule.
  • Entity- The Entity handling the project.

Image Added

Project Structure tab

The Structure tab is used to define and organize the breakdown of work within a project. It serves the following purposes-

  • Task Code - Unique identifier for each task following the WBS hierarchy.

  • Item & Content - Name and description of the task.

  • Quantity & Unit - Specifies the task scope.

  • Planned Start/Finish Date - Scheduled execution timeline.

  • Plan Days - Duration between start and finish dates.

  • Weight (%) - Contribution of the task to the overall project progress.

  • Predecessors - Task dependencies.

Image Added

Note- This document is always connected to the most recent version of the estimation. Suppose any modifications, such as revisions or variation order, are made to the estimation. In that case, the system will detect them and notify that the current schedule is outdated, prompting an update.

Image Added

Gantt Chart View 

A Gantt Chart is a timeline view of project tasks, showing start & end dates, duration, and dependencies.

Allows drag-and-drop of tasks to set dependencies.

Supports predecessor linking (Finish-to-Start, Start-to-Start, etc.)

...

Scale, Refresh, and Print tools are available.

...

Visual indicators help you identify cancelled or modified tasks.

7. To-Do Items (Separate Topic)

To-Do Items are generated from the Project Schedule. They represent planned work and are required for:

  • Generating Progress Reports

  • Assigning tasks to users

  • Managing day-to-day task execution

Note: You cannot create To-Do items unless a Project Schedule exists.

...

Indicators (x) help users identify cancelled or cancelation BOQ lines, which are not actual in the latest Project Estimates document.

Image Added

3. To-Do Items 

To-do items are internal tasks linked to specific project tasks or revenue line items. They are not visible to the client but help track internal work progress. The "Add To Do Item" button becomes available when the “Use Business Process and Tasks” option is checked in Contracting Settings.

Image Added

It represents the internal steps the team must take to complete those deliverables. It can be created per project task or revenue line.

Image Added

  • Duty- Describes the task to be done..
  • Assign to - Select who is responsible, an individual or a team member.
  • Priority- Sets urgency level (e.g., High, Medium, Low).
  • Planned Start Date- When the task is scheduled to begin.
  • Due Date- Deadline for completion.
  • Project- Links the task to its parent project.
  • Project Task- Connects to a specific scheduled item in the master plan.
  • Weight- Indicates task’s importance or contribution to project progress (expressed as a percentage).
  • Topic- Reference section for categorization or discussion thread.
  • Author- Person who created the task entry.
  • Start Date (bottom field)- When work was initiated (can differ from planned).
  • Revision- Optional field for assigning the task to an administrator to track edits or version control.

Image Added

4. Import & Export 

The system allows data import/export from the scheduling screen:-

Export Schedule to

...

Import options allow bulk upload of task data (if supported).

...

File - Saves the current schedule (task names, planned dates, dependencies) into an Excel file; useful for sharing, external editing, or use in other software.

Import Schedule from File - Allows users to upload an Excel file with planning data (start/finish dates, dependencies).

Please note- Import/Export tools allow you to manage scheduling data in Excel, but changes apply only to dates and links, not the project structure.