how to create.

How to use

 Full project templates.

 Cost fill by templatesProject templates are ready-made templates that simplify creating new project estimates. They ensure consistency and save time by reusing standard formats and structures.

Each template contains predefined:

  • WBS (Work Breakdown Structure) or hierarchy

  • Cost and revenue structures

  • Standard tasks, UOMs, and pricing

  • Overheads and markup percentages (if applicable)

...

1. How to Create a Project Template

  • Go to the Projects Module, navigate to the Projects screen from the main menu.

Image Added

  • Click “Create.” to open a new project entry form.

  • Enter Template Details

    • Description: Name of the template (e.g., “Template MEP – ELECTRICAL”).

    • Status: Set as “New”.

    • Check ‘Is Template’: This marks the project as a reusable template.

    • Entity, Company, and Project Type: Fill these as needed for categorization.

Image Added

  • Build the Estimate Structure

    • Go to the Estimates tab.

    • Manually enter cost and revenue items or import BOQ from Excel.

    • Include WBS codes, units, prices, overheads, and markups.

  • Save
    Once the structure is complete, click Save. The project is now available as a template.

...

2. How to Use a Project Template

The Fill by Template feature allows the Project Estimate document to be automatically populated using predefined templates. These templates, stored in the database, contain standardized revenue structures that promote consistency and improve efficiency across multiple projects.

Templates are displayed according to the selected cost calculation method. For estimates where the “Cost is calculated based on revenue,” only templates with matching settings will be shown, and the same applies in the case of Independent Calculations of Costs and Revenues.

This functionality is accessible directly within the Project Estimate document.

Click on the Fill by Template option to fill in the revenue and cost tab.

Image Added

The screen is divided into two parts:

Left Side: Displays a list of all available template projects marked as templates in the database.

Right Side: Shows the revenue rows from the selected template.

Image AddedImage Added

You can select a single line, multiple lines, or all lines. To add a line to your project estimate, hover over it and click Pick. The selected line will appear in the estimate table below, where quantity and markup can be adjusted. Cost, total cost, and markup amount will be calculated automatically.

Image Added

Click Next Step once the project estimate tab is filled.

Image Added

This displays all tasks and subtasks, along with detailed revenue lines, quantity, unit cost, and markup. Click Fill to transfer this structure to the project.

Image Added

The Estimation Document will be filled out accordingly.

Image Added

If the template included cost lines linked to revenue, those links will be transferred as well. 