Track individual task progress.
Update overall project progress by accumulating detailed To-Do task updates.
Provide clear accountability per team member.
Enable automated calculation of Work Breakdown Structure (WBS) line progress based on completed To-Do items.
Administration → Contracting → Use business processes and tasks
The feature is included within the Project Scheduling and Project Progress modules.
How to use the functionality
Project Schedule → right-click BOQ line → Create To-Do Item.
Or create directly from the My To-do items screen of Project scheduling.
For details on creating and about each fielda to-do list, see 3.3.2.Project Scheduling
Suspend: Temporarily pauses the task.
Enter Progress: Opens a dialog box to record or update the task’s completion percentage.
Tasks: Opens related tasks or subtasks linked to this To-Do item.
...
Click Enter Progress, input the current progress (e.g., 15%10%), and save. The update is recorded with a timestamp in the progress history.
...