  • Track individual task progress.

  • Update overall project progress by accumulating detailed To-Do task updates.

  • Provide clear accountability per team member.

  • Enable automated calculation of Work Breakdown Structure (WBS) line progress based on completed To-Do items.

Administration → Contracting → Use business processes and tasks

Image Removed

The feature is included within the Project Scheduling and Project Progress modules.

How to use the functionality

Project Schedule → right-click BOQ line → Create To-Do Item.

Image Removed

Or create directly from the My To-do items screen of Project scheduling.

Image Removed

In the To-do items, fill in the following fields:

Image Removed

Duty: Defines the task name.

Assign to: Specifies the responsible user.

Due Date: Sets the task deadline.

Project / Project Task: Links the task to its relevant project and subtask.

Weight: Indicates task importance in progress calculation.

Priority: Defines the urgency level.

Control Buttons: Includes options to start, save, close, or update progress.

Enter Progress: Records progress against the task.

Assign Revision: Delegates responsibility for updates.

Author and Timestamps: Logs who created the task and when.

Once all details are filled, post the document.

Once all task details are filled in, post the To-Do item by clicking “Save” or “Save and Close.”

For details on creating a to-do list, see 3.3.2.Project Scheduling

Image Modified

  • Suspend: Temporarily pauses the task.

  • Enter Progress: Opens a dialog box to record or update the task’s completion percentage.

  • Tasks: Opens related tasks or subtasks linked to this To-Do item.

How to record the progress

1. Record Progress in To-Do Item
Open My Project To-do items from Project Costing.

...

Click Enter Progress, input the current progress (e.g., 15%10%), and save. The update is recorded with a timestamp in the progress history.

...

2. Update Project Progress from To-Do Items

Open the Project Progress Report, select the period and project, and click "Update Progress by To-Do Items". This functionality works within the Project Progress Report when “By To Do Items” mode is selected. The system retrieves the latest progress from the To-do items and applies it to the BOQ line. The user can also manually adjust the percentage (e.g., from 50% to 70%).

...

If progress is recorded this way, it appears in the To-Do Item progress history as "Recorded by Project Progress Document."

...