Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Requisition - An Internal document used to initiate the process of engaging a subcontractor.

  • Subcontractor Agreement - It is an internal document that defines and manages the portion of the project BOQ

  • Subcontractor Agreement Revision - Update to an existing subcontractor agreement before the subcontractor’s work begins. Typical updates include modified rates, revised terms, or changes to the scope of work.

  • Subcontractor Agreement Variation - A formal amendment to the original subcontractor agreement, reflecting changes in project scope, contract value, or deliverables after the work has commenced.

  • Advance Payment - Optional upfront amount paid to the subcontractor as per the agreement terms. Adjustment where advance payments are deducted from the total invoice amount.

  • Payment Application (Incoming) - Claim submitted by the subcontractor for work completed.

  • Payment Certificate (Outgoing) - Document issued by the internal team confirming and certifying the approved payment amount.

  • Invoice Received - Invoice provided by the subcontractor based on the certified payment.

  • Debit Note - Issued to correct overpayments or to record penalties and financial deductions.

  • Retention Claim Invoice Received - Final invoice raised for the retained amount after project completion or defect liability period.

...