The Payment Certificate Issued document records the certified value of work completed by the subcontractor's work, based on the Payment Application Received. It represents the main certification document confirming the amount payable to the subcontractor for the current period.
This document mirrors the Payment Certificate Received process but is specific to Subcontractor Agreements (SA), certifying the value of work performed under each SA.
How to Create
How to Create
The Payment Certificate Issued document is primarily generated from the received Payment Application using the Generate function, which automatically pulls in all default information.
Alternatively, it can be created manually in the Project Costing or Purchasing module.
- Project Costing→ Subcontractors Management → Payment certificate issued.
...
2. Purchasing → Subcontractors Management → Payment certificate Issued.
Main
It captures the main details of the certification:
- Company - The company for whom the payment certificate is created.
- Contract - Defines billing and certification based on the selected contract type.
Apply Retention - Withholds a specified portion of the payment according to the contract’s retention rules.
Ret. VAT at Retention Invoice - Applies VAT to the retention amount when the retention invoice is issued.
Both options are automatically set based on the linked contract and are non-editable in the document.
- Subcontractor Agreement Initial-Links the certificate to the original Subcontractor's Agreement document.
- Entity - The legal party issuing the payment certificate.
- Basis - Indicates the origin of the certificate, whether generated from a Payment Application Received or created manually to record progress.
- Project - Linked project used to auto-fill WBS, service lines, and cost tracking information in the payment certificate.
...
Progress-Used for certification of actual work completed by the subcontractor.
Advance-Used to acknowledge or certify advance payments as per the contract. Selecting this activates the Advance tab for managing prepayments instead of progress-based work.
Subcontractor Agreement Initial-Links the certificate to the original Subcontractor's Agreement document.
- Comment - Field for entering any additional notes, remarks, or internal instructions related to this certification.
Service Tab
Displays the work items or services being certified for the current period.
Subcontractor WBS - Optional code to identify work as defined by the subcontractor.
- Item / Content - Description of the work or service performed.
UOM -Unit Unit of measure (e.g., m, pcs, hrs).
Price- Unit rate as defined in the SA.
- Agreement
- Qty - Original contracted quantity.
- Amount - Original contract value.
- Payment Application
- Qty - Quantity claimed by subcontractor in the payment application.
- Amount - Claimed amount.
- % - Percentage of the agreement claimed.
- Payment Certificate
- Previous Qty - Quantity certified in prior certificates.
- Previous Amount - Amount certified in prior certificates.
- Previous % - Percentage certified in prior certificates.
- Current % - Percentage certified in the current certificate.
- Cumulative % - Total percentage certified to date, including current and previous certificates.
Quantity - Quantity of work certified in this certificate
Amount (Excl. VAT) - Certified amount excluding VAT.
VAT % - Applicable VAT rate (e.g., 5%).
Retention-
- Total (before retention) - Certified amount before applying retention.
- Retention% - The percentage of the amount to be retained.
- Retention - The calculated retention value based on the retention percentage.
- Retention VAT - VAT portion attributable to the retained amount.
VAT Amount - VAT on the non-retained portion.
Total - Final amount payable, including VAT, after retention.
- Project Task - Specific task linked to the item.Description - Detailed label or scope of work.
Project WBS - Work Breakdown Structure reference.
Requisition - Reference to the requisition document.
Comment - notes for clarification or remarks.
Summary Tab
The Summary Tab provides a consolidated view of key quantities and financial metrics throughout the subcontractor payment process, allowing quick comparison across different stages:
Agreement - Original contract quantity and value agreed with the subcontractor.
Payment Application - Quantity and value claimed by the subcontractor in submitted applications.
Payment Certificate - Quantity and & value approved or certified by to the main contractor.subcontractor
Invoiced - Quantity and value formally invoiced by subcontractor for payment.
Each section displays:
Qty - units of work.
Amount - value of the work.
Deduction Tab
Used to record amounts that need to be deducted from the total payable value of a subcontractor’s payment certificate. Each line reflects a specific deduction applied according to contract terms, retention rules, or penalties.
Item - The deducted service, work item, or reason for deduction.
Qty & Price - Quantity and unit rate applicable for the deduction.
- VAT - Tax status for the deduction, indicating whether VAT applies or notContent - Details or description of the deduction.
Quantity - Quantity being deducted.
UOM (Unit of Measure) - Measurement unit for the quantity.
Price - Unit rate of the item.
VAT% - Applicable VAT rate
- VAT Amount - VAT calculated on the deduction.
Note: VAT % and VAT Amount in this tab are for calculation purposes only and will not be posted as output VAT in the future Invoice Received. Proper VAT posting can be done by issuing the Invoice document for subcontractor's deduction-related transactions.
Amount - Total deduction value before VAT.
Total Amount - Total deduction amount including VAT (Net + VAT).
- Subcontractor WBS - Optional code to identify work as defined by the subcontractor
GL Account - Ledger account where the deduction is posted.Project WBS - Work Breakdown Structure reference for cost allocation.
Department - Department responsible for or related to the deduction.
Business Activity-Type of business activity associated with the deduction
Income Item-Income category or account linked to the deduction
Comment-Free-text field for notes or explanations about the deduction
Advance Offset
The offset can be entered manually or carried forward from the Payment Application received. It doesn’t perform the actual financial offset but helps prefill the offset value in the progressive invoice, avoiding the need for re-selection.
Additional Information
Includes optional and reference fields for internal notes or cross-references:
...
Two standard print layouts are available for subcontractor Payment Certificate documents. The structure is flat (non-hierarchical) across all forms:
a) Payment Certificate - Detailed layout showing certified items, deductions, and payable values.
...