The Variation Function allows for the creation of additional quotation documents for work not included in the original project estimate. It also supports modifications to the initial scope or agreement once the project is active.

To enable this functionality, it must be configured via:
Administration → Contracting → Quotation Process
(Ensure the Quotation + Revision + Variation option is selected)

Image Added

When a project reaches Active status, the "Create Variation Order" button becomes available in the project estimate section. This opens the variation workflow.

Image Added

Image Added

In the variation estimation document, the estimate lines are locked and cannot be edited directly. To make changes:

  • Change Row – Marks an existing line as cancelled. The system creates a reversal transaction and generates a new editable line for modifications.
  • Cancel Row – Reverses the selected line by marking it as cancelled, without creating a new editable line.
  • Add Line – Allows the addition of new lines to account for extra or additional work.

Image Added

Variation acceptance functionality

To activate the feature, Contracting Settings → Administration Section→ Use Variation Estimation Acceptance. 

Image Added

Once enabled, the system will process all project estimate documents marked as Variation and automatically update the "Accepted" column in the Revenue tab for any lines added in the current or previous variation orders.

Image Added

Once a variation order is posted, the changes are not considered accepted by default. A new "Accepted" column appears in the revenue section, but it remains empty until the client formally confirms the variation. Client acceptance is not a mandatory option.

If needed, a new quotation document can be generated from the variation and shared with the client for approval. This quotation includes reversed lines, newly added items, and the total value of the proposed changes.

Image Added

Once the client approves, mark the variation as accepted in the system. You’ll be prompted to enter the acceptance date. Upon acceptance:

  • Revenue reports and project data are updated.

  • New lines are reflected in the financials.

  • Contracts are adjusted if needed.

Image Added

Users with full access can accept variations manually. Restricted users will see the accepted status set automatically and cannot change it. If no further processing has occurred, accepted variations may be cleared, subject to access rights.

Image Added

This function ensures accurate, auditable handling of changes, whether they arise from client requests, internal corrections, or evolving project needs. Costs are applied when the variation is posted, but revenue is recognized only after acceptance (if required).