In long-term planning, a resource remains assigned from its start date until it is manually released using the release-from date in the resource scheduling screen. Direct replacement of a resource cannot be handled through the adjustment document because resources are treated as being assigned indefinitely. To assign a replacement, a new Resource Planning document must be created for the new resource, beginning on the intended start date.