The Project Progress Billing Report combines financial and billing information for active projects, showing the movement from estimated values to billed, certified, and invoiced amounts.

Structure

Generate - Runs the report based on the selected filters or parameters.

Find - Search within the report for specific projects, tasks, or items.

Collapse/Expand Groups - Show or hide grouped WBS sections.

Print Button - Opens a print preview or sends the report directly to a printer.

Fit to Screen/Zoom Button - Adjusts the layout to fit the screen or zooms in on specific sections.

Search Button (Magnifying Glass) - Advanced search tool for locating specific records.

Edit Mode Button - Allows modifications or notes to be made directly in the report.

Save Disk - Export the report in formats like Excel or PDF.

Send - Share the report via email or other channels

Report Fields

Project-Name or description of the project.

Project WBS- The detailed breakdown of tasks and BOQ lines within the project.

Estimated- Represents the planned quantities and corresponding contract values for each project before any work begins

  • Quantity- Planned quantity for the project 

  • Amount (Cur)- Total planned estimated contract value for that quantity.

  • Discount (Cur)- Any discount applied to the estimated amount.

...

Payment Application (PA)- The official request to get paid certificate for the work done during a specific period. It shows the value of the work the contractor is claiming.

  • Quantity- The actual amount value of work being billedcompleted, as checked on-site by contractor

  • Amount (Cur)- Value claimed based on progress. 

  • VAT (Cur)- Tax on the claimed amount.

  • Retention (Cur)- Amount withheld as retention.

  • Retention VAT (Cur)- VAT portion related to retention.

  • Progress %- Percentage of work billed.

...

Payment Certificate (PC)- Represents the amount of payment approved and certified by the client after reviewing the contractor’s payment application. It confirms how much of the claimed work is officially accepted for payment.

  • Qty-Approved Certified progress quantity.

  • Amount (Cur)-Approved Certified payment value.

  • VAT (Cur)-Tax on the approved certified amount.

  • Retention (Cur)-Amount withheld as retention.

  • Retention VAT (Cur)-VAT related to the retention.

  • Progress %- Percentage of work certified as payable.

...

  • Report Date: Limits the report to data within till the selected perioddate.

  • Entity: Option to generate the report for a specific entity.

  • Project: Option to generate the report for a specific project.

...