Send - Emails or forward the report to another user or contact.

Report Fields

  • Project:- Description of the project
  • Code WBS, Project Task:- Project tasks broken down by Work Breakdown Structure (WBS)
  • The Item column displays all detailed subcomponents, materials, equipment, or activities associated with a project task, providing a granular view of their associated costs or revenues.Item- Column lists detailed components of each task
  • Quantity (Opening, For Period, Closing, Estimated, Pending) measures the physical progress of work.

    1. Opening Balance - cumulative quantity completed up to the start of the period.

    2. For Period - Quantity of work done in the current reporting period.

    3. Closing Balance - cumulative quantity completed to date (Opening + For Period).

    4. Estimated - planned quantity for the task.

    5. Pending - remaining quantity to be executed (Estimated - Closing).

...

  • Amounts reflect the financial side of progress.

    1. Opening Balance - cumulative recognized amounts from prior periods.

    2. For Period - value recorded in the current reporting period.

    3. Closing Balance - cumulative recognized value (Opening Balance + Actual Amount (For Period)).

    4. Estimated - planned value for the task.

    5. Pending - balance not yet recognized (Estimated - Closing). 

  • Amount Completion % shows progress in percentage termshow much of the work or revenue has been completed, expressed as a percentage.

    Formula

    :

    -
    Amount Completion % = (Closing Balance ÷ Estimated Amount) × 100

    Example-
    Closing Balance = 11,282.30
    Estimated Amount = 133,190.10
    Calculation- (11,282.30 ÷ 133,190.10) × 100 = 8.47%

    Meaning of Values-

    1. Positive % - Work progress has been made and recognized.

    2. 0% - no No progress has been recorded.

    3. Negative % - reversals Reversals or corrections reduce recognized revenue progress below zero.

Filter

Period:- Define the report’s start and end dates; only data within this range will be included.

Without templates:- Excludes entries that are based on templates.

Show amounts:- When enabled, displays amount columns and details; otherwise, only quantity columns are shown.

Entity:- Optionally select specific entities.

Project: - Restricts the report to the chosen projectsselected projects.

Item:- filter based on a specific item.

...