  • Project:  Description of the project
  • Code WBS, Project Task: Project tasks broken down by Work Breakdown Structure (WBS)
  • The Item column displays all detailed subcomponents, materials, equipment, or activities associated with a project task, providing a granular view of their associated costs or revenues.
  • Quantity (Opening, For Period, Closing, Estimated, Pending) measures the physical progress of work.

    1. Opening Balance - cumulative quantity completed up to the start of the period.

    2. For Period - work done in the current reporting period.

    3. Closing Balance - cumulative quantity completed to date (Opening + For Period).

    4. Estimated - planned or target quantity for the task.

    5. Pending - remaining quantity to be executed (Estimated - Closing).

Image RemovedImage Added

  • Amounts (Opening, For Period, Closing, Estimated, Pending) reflect  reflect the financial side of progress.

    1. Opening Balance - cumulative recognized amounts from prior periods.

    2. For Period - value recorded in the current reporting period.

    3. Closing Balance - cumulative recognized value (Opening + For Period).

    4. Estimated - budgeted or planned value for the task.

    5. Pending - balance not yet recognized (Estimated - Closing). Example: if Design Fire Fighting Pump has an estimate of 31,850 but a closing balance of -3,185, pending is 35,035, showing a reversal. 

  • Amount Completion % shows progress in percentage terms.

    1. Formula: (Closing Balance ÷ Estimated Amount) × 100.

    2. Positive % - progress made and recognized.

    3. 0% - no progress.

    4. Negative % - reversals or corrections reduce recognized revenue below zero.

Example: Construction Scope estimated at 254,800, actual -6,370, equals -2.5% completion.

Image RemovedImage Added

Filter

Period: Define the report’s start and end dates; only data within this range will be included.

...