Send - Emails or forward the report to another user or contact.

Report Fields

  • Project:  Description of the project
  • Code WBS, Project Task: Project tasks broken down by Work Breakdown Structure (WBS)
  • The Item column displays all detailed subcomponents, materials, equipment, or activities associated with a project task, providing a granular view of their associated costs or revenues.
  • Quantity (Opening, For Period, Closing, Estimated, Pending) measures the physical progress of work.

    • Opening Balance - cumulative quantity completed up to the start of the period.

    • For Period - work done in the current reporting period.

    • Closing Balance - cumulative quantity completed to date (Opening + For Period).

    • Estimated - planned or target quantity for the task.

    • Pending - remaining quantity to be executed (Estimated - Closing).

...

Example: Construction Scope estimated at 254,800, actual -6,370, equals -2.5% completion.

Filter

Period: Define the report’s start and end dates; only data within this range will be included.

Without templates: Excludes entries that are based on templates.

Show amounts: When enabled, displays amount columns and details; otherwise, only quantity columns are shown.

Entity: Optionally select specific entities, such as departments or companies.

Project: Restricts the report to the chosen projects.

Item: Optionally filter for particular items or subcomponents within a project.