  • Purpose of the document.
  • how to create.
  • main tab attributes. explain about contract settings. 
  • Can be used for issuing Advance invoice.
  • Table: how to fill, columns description.
  • Advance offset button and form. for planned advance offset.
  • Summary linked table .


The Payment Certificate Received document is used to record and confirm the certified value of work completed on a project, as assessed and issued by the client or consultant.

It serves as an official acknowledgment of:

  • Work progress approved by the client

  • Amounts certified for invoicing

  • Retention, VAT, and deductions as per contract

This document is a critical step in the progress billing cycle. Once recorded, it can be used to generate a Progressive Invoice, Offset prepayments, and Track certified progress and compare with applied progress.

Project Costing→ Project Progress→ Payment Certificates Received.

Image Added

How to create

Click Create, then select the Project. The certificate details will be automatically filled based on the selected project.

Image Added