Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

The Description and Project fields are mandatory.


  • In the DescriptionProject field, type a clear and concise description of select the project task. This description will identify the project task in the project task liststo which this task is related.
  • In the Parent Task Project field, select the project to which specify the task that includes this task is related.
  • In the WBS Code field, enter the code assigned to the task.
  • In the In TaskDescription field, specify the task that includes this tasktype a clear and concise description of the project task. This description will identify the project task in the project task lists.
  • Use the Milestone checkbox to mark this task as a milestone within the project.

  • Specify the planned start date in the Planned Start Date field and the expected completion date in the Finish field.

  • The Start Date (Plan) and End Date (Plan) fields allow you to define the planned duration of the task.

  • Once the task has started or been completed, the Start Date and End Date fields can be used to capture the actual dates.

  • Use the Details text box to add any relevant information about the task

...

Then, select a Predecessor Project Task—this ; this is a task that must be completed (or started) before the current task can begin or proceed. Also, choose its Dependency Type, which defines the relationship between the tasks (e.g., finish-to-start, start-to-start, etc.).

...