To add a project task, click the Create button on the toolbar. To edit the existing one, double-click the line with its name. You can also select the line, right-click it, and select Edit or click on the toolbar: More actions > Edit.
1.4.1: Adding a Project Task
This tab provides you with main information on the project task: project, planned dates of its start and finish. As the project moves through different stages of its life cycle, the dates of project task's actual start and finish can be added.
...
In the Details text box, you can enter any information that is relevant to the project task.
1.4.1.1: Employee’s tab
The information on this tab is optional.
...
Click Save to save the entered data.
1.4.1.2: Predecessor’s tab
The information on this tab is optional.
...