    There is a Production Calendar, that may be changed according to some needs, or a new calendar or groups of calendars may be created.

Image Removed

2. Create a new calendar and fill its name as a necessary field. Set     Click on Create option to create a new Work Days Calendar and a dialog box will appear.

Image Added


2. Fill the box with description and set a year in which changes need needs to be applied or start of this calendar.


3. Select a workweek scheme using the Reset button - the chosen scheme is populated for the whole year automatically.
There are three workweek schemes:

...

6. Save changes. Now there are two calendars in the system.


7. Use the different calendars in different Entities, for different departments or different Working Schedules:The required work calendar should be according to the requirement i.e. in Entities, Departments or Employee schedule (Work Schedule).